In the last part of this
article, Humphrey looked at the history of the Harrier force from 1998 until
the start of the 2010 SDSR. It left off with the Harrier GR9 force having been
reduced to just 10 FE@R, and looking vulnerable ahead of a long awaited Defence
Review.
The 2010 SDSR was a review
that was always expected, although many political games were played between the
three parties in the run up to the election. At different times, all three
major parties committed to conducting a review, although the MOD couldn’t formally
do any preparatory work until the then Labour Government had confirmed it too
would hold one. Its always slightly embarrassing for the Civil Service to be planning
ahead for the next Government agenda, while your current Government is yet to
commit to that particular course of action.
Nonetheless, in the run up to
the 2010 election, its fair to say a lot of preparatory ‘think tanking’ was
done in various quarters, considering some of the likely exam questions that
would crop up in a Defence Review. This author remembers discussing with senior
officers the need to begin slowly preparing the groundwork for a Defence Review
as early as 2008 – this wasn’t a political statement, more an acceptance that
whoever won the election would want to review Defence. By the time Liam Fox
arrived at the MOD in May 2010, a lot of work had gone into establishing the
underpinning work that would later inform the SDSR.
The SDSR provided the first chance
in 12 years to review where the UK was heading, and to try to take stock of the
massively overheated equipment programme. From the outset it was clear that
cuts would be required to try and return the funding into a balanced position,
and that everything was up for grabs.
Humphrey was deployed on OP
HERRICK at the time, so had no involvement in the SDSR at all. Talking to
friends who were involved, it was clear that it was a challenging time, as the
MOD had to try to put together a force structure which would meet the stated
goals of the National Security Strategy, achieved military success in
Afghanistan and met the various defence outputs that together formed the
Military Tasks for the MOD.
This was not an easy task. On
the one hand, planners were being required to sort out a budget which had to
fund a disproportionately large fighting force until 2015, meaning manpower
cuts, which was where real savings could be made, could not occur in large numbers until this point. They then had
to consider how to fund a military that would need at least four – five years
to recover from OP HERRICK and associated tasks in the 2015 – 2020 period. In
theory then, by 2020 the military would need to be operating a force capable of
conducting a full range of contingency operations. In broad brush terms, the
challenge the planners had looked something like this.
Time Frame
|
Challenge
|
Issues
|
2010-2014
|
Sustain Operation HERRICK
(10,000 ground troops) as Defence Main Effort, and recover to UK. Exceptionally
limited other capability.
|
Cannot easily reduce size of
Army and supporting forces without affecting HERRICK.
|
2015-2019
|
Reorganise from Op HERRICK,
regenerate forces and deliver limited expeditionary capability.
Implement SDSR2015 findings.
|
Window to deliver major
reduction in force levels without impacting on operational output.
|
2020+
|
Regenerated forces capable
of delivering full range of Military Tasks.
Implement SDSR2020 findings.
|
Harder to put redundancies
through as UK able to conduct discretionary ops again.
|
Having identified the three
main time periods, each of which had very different requirements, planners had
to consider how to build a force that could meet the likely military tasks. In
broad brush terms this meant build a range of force packages which could
produce a different series of outputs. If you look at the SDSR, then the
outputs stated – such as maintaining a 30,000 strong three brigade force in the
field for six months, through to long term sustainment of 10,000 troops on
discretionary operations is a direct reflection of the force packages
considered. In other words, all the equipment in use today is ascribed to be
able to deliver to part of the force packages set out in the SDSR. Everything
has a place, no matter how hard it may be to see where it is at times!
While the argument over what
the force should look like was going on, another series of debates was occurring
over what was affordable, both as in service equipment and as new equipment. It
was very clear that there simply wasn’t the money in the system to fund the
forward programme. Part of the challenge was the combination of an
overcommitted defence budget, desperately trying to fund the cost of sustaining
operations in Iraq and Afghanistan for most of the previous decade, and
significant cost growth in many major programmes. This, coupled with a
political unwillingness to cancel major programmes meant that the budget was
completely out of kilter.
As part of these budget cuts, it was clear
that there was only sufficient funding in the system for two fleets of Fast Jet
aircraft to run through until 2020. At the time the UK planned to operate the
Typhoon, Tornado GR4 bomber and the Harrier GR9 until the 2019-2024 timeframe.
The problem with running FJ
fleets is that no matter how many airframes you reduce in front line service,
there will always be costs that cannot easily be saved. You have to have
support contracts, you need to have maintenance support, you need a training
pipeline which provides fitters, engineers, pilots, and all the other personnel
needed to make an aircraft fly. You need to run dozens of training courses across
multiple ground schools in the various pieces of ordnance, technology, engines
and kit and all this comes at a significant cost. You cannot turn this off
while the aircraft remains in service, so reductions in FJ are only useful if
they come with a wider reduction in billing.
For the MOD, it was clear that
the only way to meet the very large sums required was to take an entire fleet
of aircraft out of service, and enjoy the costs of fleet reduction, reduced
training, manpower, real estate and so on.
 |
| Tornado GR4 (Copyright Wikipedia) |
The case for Tornado.
It seems to be clear that both
Tornado and Harrier were considered for possible deletion. Ultimately, the
decision was taken to retain the Tornado over the Harrier force. But why?
At its simplest the case for
Tornado was far more credible than Harrier. The Tornado force of some 140
airframes had been in service for some 30 years by this point, although as with
Harrier, the fleet had been significantly upgraded. It seems that about 60-70
aircraft (Humphrey can’t find the exact figures) were attributed as FE@R. The aircraft were scheduled to
remain in service until 2024 (or thereabouts) providing the UK with a longer
term strike capability than Harrier, which was due to go in about 2016-2018.
The fleet was cleared to carry
a much wider range of munitions than the Harrier force, including ALARM, Brimstone
and Storm Shadow missiles, which provided the UK with a credible weapons
package. The funding for the Harrier to carry such missiles had never been
approved, meaning that it had a theoretical capability only.
By contrast the Harrier was
leaving service sooner than the Tornado, and far less airframes were available.
It would take time and money to bring the Harrier fleet back up to readiness
for the various tasks already ascribed to the Tornado fleet. Any deletion of
the aircraft fleet would probably need to be done by the end of the financial
year, meaning if it were withdrawn, then the UK would at a stroke lose its
ability to deploy ALARM, Brimstone and Storm Shadow. Losing a highly capable cruise missile platform, and exceptionally useful 'wild weasel' and anti-tank platform would have been far more damaging to the long term defence argument than losing the Harrier.
The final problem was that for
the Harrier force, the main rationale to remain in service was the need to
sustain seedcorn capability for the carrier fleet. The decision to alter CVF to
a CTOL platform removed this argument at a stroke. CTOL was so sufficiently
different from STOVL that a whole new set of skills would need to be relearned –
hence the deployment of pilots to train on the F18.
If CTOL was coming in to
service in 2018, and the UK was committed to Afghan Operations until 2015, and
then recovering from 2015-2020, then a reasonable assumption could be made that
Harrier was a lower priority. After all, there would be limited likelihood of an operation requiring carriers to occur, and with the Harrier fleet committed to HERRICK, then there would be little chance of finding spare pilots to engage in sea deployments (Humphrey has heard friends claim that the RN was into single figures for fully qualified carrier pilots by the end of the Harriers life).
Tornado by contrast was
committed to Op HERRICK (some 12 aircraft by that point were in Kandahar) and had
no programmed successor entering service before 2020. The Harrier fleet would
need to be assigned to replace Tornado, and given the paucity of pilots, and
wider resource for Harrier, this would mean making it a single deployment.
In other words, had the decision
been taken to delete Tornado, then Harrier would have had to have gone back to
Afghanistan, to replace the air cover lost by removing Tornado. A fleet barely
half the size of the GR4 fleet would have been probably broken trying to
sustain 12 aircraft, particularly when deploying just six airframes caused
problems during its previous deployment.
With the likelihood that all
the Harrier force would have been assigned to Op HERRICK, or supporting maintaining
a token contingent capability elsewhere, then the likelihood of seeing a
carrier deployment would have been slimmer than ever. It is essential to
understand that had Harrier been kept in the SDSR, then the Royal Navy would
still not be doing any fixed wing carrier flying today.
Could the RN have funded the
Harrier alone though? Its often suggested
that the RN should regain control of its fighter squadrons and use the
money to fund its force directly. A great argument in theory, which ignores a
salient fact. The RN over the last 14 years could have made sacrifices to find
the funding – under older arrangements it could have put forward plans to
sacrifice other capabilities directly to fund the Harrier. It chose not to do
so, preferring instead to try to find savings through joint work.
Latterly, as procurement
budgets got tied into a very complicated mixed of ‘capability areas’ it could
have found commensurate savings elsewhere in the budget to enable funding to be
found to run on Harrier. This would have been complex – needing the RN to find
sufficient funding to enable resources to run front line squadrons plus a
training pipeline, plus all the various elements that supported keeping
aircraft flying. This isn’t to say it couldn’t have been done, but it would have
needed work to find funding cuts elsewhere which would generate sufficient
savings to keep Harrier alive.
Again, it is telling that
despite the many reviews of the last 14 years, the RN has chosen to put other
capabilities ahead of funding the Fleet Air Arm. No matter how often people may
cry foul about the RAF, the fact the RN was unwilling, or unable to find the
money should not be forgotten either.
 |
| The great hope of the Fleet Air Arm. JSF and CVF |
Look – No Carriers!
The other problem was that the
Royal Navy would probably not have had any aircraft carriers to fly the
Harriers off anyway. The original disposal plan for the Invincible class saw
the first going in 2010, followed by ILLUSTRIOUS in 2012, and finally ARK ROYAL
in 2015, while OCEAN ran on. At this point
CVF would have been working up and theoretically embarking harriers in
lieu of JSF.
In reality the decision to
delay CVF in an earlier planning round meant that conversion to CTOL became
feasible. Had the original timelines been adhered to, then QUEEN ELIZABETH
would have been entering final stages of construction as the SDSR came along,
and could have borne Harriers. The RN decision to delay CVF in the 2008-2009
period meant CTOL conversion became feasible, and a carrier gap became reality.
The only difference between
pre and post SDSR for the RN carrier fleet was losing HMS ARK ROYAL slightly
early. The RN was always going to be a single carrier fleet by 2012. More
importantly it is often forgotten that HMS OCEAN has always been due a two year
refit in the period 2012-2014.
However you look at it, even
if SDSR had kept Harrier, then the sole UK carrier in service, most likely ARK ROYAL
would probably have been required to re-role into an LPH anyway to cover for
HMS OCEAN. In other words, if SDSR had kept Harrier, the RN would still not
have a fixed wing carrier capability right now. It would instead be focused on delivering
an LPH capability, which if anything has been shown by recent operations to be
of more value to the UK than a carrier.
The key message to take away
is that SDSR was effectively irrelevant to the future of the RN fixed wing
flying. The decisions taken in earlier spending rounds had sealed the fate of
Harrier. The reduction in readiness, and the decision to delay CVF entry to
service meant the RN would have struggled to send a carrier to sea.
So, by 2015 the RN would have
reduced to a single carrier (HMS OCEAN), unable to operate Harrier aircraft.
With HMS QUEEN ELIZABETH not due in till 2016 at the earliest, even then
configured as an LPH, a Harrier OSD of 2018 and with the CVF conversion to CTOL
predicted to take longer, it’s clear that even if Harrier had been run on to
2018, the UK would have had a capability gap. In realistic terms, it’s hard to
see the UK having the capability, even under pre SDSR plans, to put a credible
harrier force to sea beyond 2012. Beyond this point the focus shifts to
providing LPH capability, to keep the amphibious task group skills alive, as a
higher priority than running old jets on.
To this author, a convenient ‘rewrite
of history’ has occurred over the Harrier. Its very easy to sit and make out
that the RNs beloved fixed wing aviation capability was destroyed in SDSR,
enabling sailors to sit in bars and lambast RAF deviousness. In this narrative
the RN would right now be putting mighty warships to sea armed to the teeth
with the GR9, and awaiting the arrival of CVF and its bright future.
Such a narrative is utter
rubbish. At best the most the RN could have hoped for between 2012 and 2018 was
the occasional deployment of a small contingent of RAF aircraft to try and keep
fixed wing skills alive. This would have been fleeting and dependent on other
tasking not needing the aircraft for shore based work. If Harrier had been kept
on from SDSR, then it would have been deployed on HERRICK, and its likely that
a ‘delete ARK ROYAL’ option may well have been considered anyway, as the
reality of limited carrier operations became clear.
This authors personal view is
that in the eyes of the RN, securing the future capability was a more important
battleground than retaining a hugely limited present capability. Hence the
realisation that if CVF was secure, actually retention of Harrier was less
important to fund as long as a successor was confirmed. In the case of CVF, the
CTOL option gave the RN a good opportunity to build a force package which
enabled for deletions of high profile capabilities which actually offered
little in the way of deployability, such as ARK ROYAL and the supporting AORs,
and instead focus resources on two areas – sustaining the escort fleet and the
amphibious assault capability. Humphrey believes that if push came to shove,
and it had been decided to save the Harrier, then the corresponding savings
would probably have come from even greater reductions to the surface fleet, or
the complete removal of the amphibious capability – on the grounds that there
was little else left to take.
The RN made a compelling case
in SDR for a power projection focused navy, which as will be seen when ELLAMY
is discussed, made an incredible contribution to maritime operations in Libya.
Had the RN sacrificed more ships, marines and amphibious ability to pay to keep
a small number of Harriers at sea, then this would have been far more damaging
to the long term national interest of the UK.
Instead, accepting a small
risk in terms of deployability but continuing to build up the training pipeline
and working on skills retention, has left the RN in the best situation in a
bleak world.
Be in no doubt, the best case
scenario would have seen the RN remain in the carrier business and also kept
other assets too, but to play that game required more funding than was
available. Instead the RN has managed to keep itself reasonably balanced,
accepting short term limited risk versus long term capability.
That concludes part two of
this series. The next part will look at the ELLAMY environment, and also move
onto look at the wider post SDSR environment, and also address the myth that
the RAF ‘won’ the SDSR. It will also look at what was really lost in terms of capability
delivery and try to look at wider lessons for the Armed Forces.